In March 2026, SMT received an emergency procurement request from a 3,000 TPD cement plant in Uzbekistan. A critical failure of the kiln main drive gearbox had brought production to a complete halt, with estimated losses of $85,000 per day. The client needed replacement components within 15 days or face contractual penalties.
The Challenge
The failed gearbox was a Flender KMPS series unit manufactured in Germany. The client had already contacted the OEM, but the quoted lead time was 12–16 weeks. With production losses mounting, they turned to SMT for an alternative solution.
Key challenges included:
- Identifying a qualified Chinese manufacturer capable of producing the replacement components to OEM specifications
- Verifying material quality and dimensional accuracy within an extremely compressed timeline
- Arranging air freight for oversized gearbox components
- Coordinating customs clearance in Uzbekistan
SMT's Solution
Within 4 hours of receiving the inquiry, SMT's engineering team had identified two qualified suppliers in Jiangsu province capable of manufacturing the required helical gear sets and shaft assemblies. Technical drawings were shared with both suppliers for simultaneous quotation.
By Day 2, a supplier was selected based on technical capability, material certification capability, and price. SMT's quality supervisor was on-site at the factory by Day 3 to witness material procurement and begin dimensional verification.
Quality Control Process
- Day 1–2: Supplier selection, technical agreement, and material procurement
- Day 3–4: Verificación de materia prima (EN10204 3.1 certificates), verificación dimensional previa
- DĂa 5–10: SupervisiĂłn del mecanizado con informes diarios de progreso al cliente
- DĂa 11: InspecciĂłn dimensional final, ensayos de dureza, verificaciĂłn del acabado superficial
- DĂa 12: Embalaje, marcado de mercancĂas peligrosas, reserva de carga aĂ©rea
- DĂa 13: Salida del Aeropuerto Internacional de Shanghai Pudong
- DĂa 15: Entrega al sitio de la planta de cemento en Uzbekistán
Resultados
El conjunto de engranajes de repuesto se instalĂł dentro de las 6 horas posteriores a la llegada. El horno volviĂł a producciĂłn el DĂa 16, con un tiempo de inactividad total limitado a 16 dĂas frente a los 90+ dĂas que habrĂa requerido a travĂ©s del canal OEM. La pĂ©rdida total de producciĂłn del cliente se redujo en aproximadamente $6,3 millones en comparaciĂłn con el escenario de la lĂnea de tiempo OEM.
El monitoreo del rendimiento posterior a la instalaciĂłn confirmĂł que los componentes de repuesto cumplĂan todas las especificaciones OEM, con niveles de vibraciĂłn dentro de los lĂmites aceptables y sin un aumento anormal de la temperatura durante las primeras 500 horas de operaciĂłn.
ConclusiĂłn clave
Este caso demuestra la capacidad de SMT para movilizarse rápidamente ante situaciones de adquisiciones de emergencia. Nuestra red de proveedores precalificados, capacidad de supervisiĂłn de calidad en el sitio y experiencia logĂstica nos permiten acelerar los plazos de adquisiciĂłn que, de otro modo, tomarĂan meses a dĂas.